Constructors’ crews safely and successfully set girders for a bridge located on the Fremont Southeast Beltway project for the Nebraska Department of Transportation. The project began in September 2020 and is estimated to finish by the end of October 2021.
The goal of the project is to construct a 389’ long x 88’ wide two span concrete girder bridge. The girders span over the UPRR mainline tracks and Old Highway 275. Each girder is 168’ in length and weighs approximately 85 tons.
Concrete Industries supplied the concrete girders and Western Sand & Gravel is supplying granular backfill material.
The general contractor is Graham Construction and Constructors is a subcontractor on the project.